Two conductors in a service look similar, get called the same thing in conversation, and are sized from two completely different tables. Mixing them up is the most common grounding error in the trade, and it shows up on exams as reliably as it shows up in panels.

GEC and EGC are different animals

Grounding electrode conductorEquipment grounding conductor
JobConnects the system to the earth electrodeProvides a fault return path to the source
Runs fromService or separately derived system to the electrodeWith the circuit conductors, to every enclosure and device
Sized fromThe service-entrance conductorsThe overcurrent device rating
Table250.66250.122
Clears faults?NoYes, this is its entire purpose
Diagram contrasting the grounding electrode conductor running from the service to the earth electrode with the equipment grounding conductor running with the circuit conductors, showing that each is sized from a different table
Two conductors, two jobs, two tables. Mixing them up is the most common grounding error.

The earth is not a fault clearing path. A ground rod does not trip a breaker. The GEC stabilizes system voltage relative to earth and provides a path for lightning and utility surge events. The conductor that actually clears a ground fault is the EGC, back to the source. People who install a rod and consider the equipment grounded have this backwards.

Table 250.66: sizing the GEC

Size from the largest ungrounded service-entrance conductor, or the equivalent area for parallel conductors.

Largest service conductor (copper)Copper GECAluminum GEC
2 AWG or smaller8 AWG6 AWG
1 or 1/06 AWG4 AWG
2/0 or 3/04 AWG2 AWG
Over 3/0 through 350 kcmil2 AWG1/0
Over 350 through 600 kcmil1/03/0
Over 600 through 1,100 kcmil2/04/0
Over 1,100 kcmil3/0250 kcmil
GEC AND EGC, TWO DIFFERENT TABLES

The app keeps 250.66 and 250.122 separate so you do not size off the wrong one.

The caps that override the table

This is the part that makes the whole thing manageable, and it is the part people forget. The required size to a specific electrode type is capped regardless of what the table says.

ElectrodeCap on required GEC size
Rod, pipe or plate electrodeNot required larger than 6 AWG copper
Concrete-encased electrodeNot required larger than 4 AWG copper
Ground ringNot required larger than the conductor used for the ring
Worked example — 400 amp service

Service-entrance conductors are 500 kcmil copper. Electrodes are a concrete-encased electrode plus two driven ground rods.

From Table 250.66: 500 kcmil falls in the "over 350 through 600 kcmil" row, so the table value is 1/0 copper.

To the concrete-encased electrode: capped at 4 AWG copper.

To the ground rods: capped at 6 AWG copper.

Practical result: if your only electrodes are rods and a concrete-encased electrode, you never install the 1/0. The caps govern. The 1/0 would be required only for a run to an electrode with no cap, such as a metal water pipe electrode.

That example is why "just run 1/0 to be safe" is the wrong instinct here. It is expensive, hard to terminate on a rod clamp, and unnecessary.

Table 250.122: sizing the EGC

Size from the rating of the overcurrent device ahead of the circuit, not from the conductor size.

OCPD ratingCopper EGCAluminum EGC
15 A14 AWG12 AWG
20 A12 AWG10 AWG
60 A10 AWG8 AWG
100 A8 AWG6 AWG
200 A6 AWG4 AWG
300 A4 AWG2 AWG
400 A3 AWG1 AWG
600 A1 AWG2/0
800 A1/03/0
1000 A2/04/0
Where ungrounded conductors are increased in size, for voltage drop or any other reason, the equipment grounding conductor must be increased proportionally. This is routinely missed on long runs where the phase conductors were upsized two sizes and the ground was left at the table value.

Installation rules that fail inspections

Continuity

The GEC must be installed without splice or joint except by specific permitted means: irreversible compression connectors listed for the purpose, exothermic welding, or connection to busbars and certain listed fittings. A wire nut is not one of them.

Protection

A 6 AWG or larger GEC may generally be run along the surface without additional protection where it is not subject to physical damage. Smaller than 6 AWG requires a raceway or armor. Where a ferrous raceway is used, it must be bonded at both ends to the conductor inside it, otherwise the raceway acts as a choke and dramatically increases the impedance of the path.

Aluminum restrictions

Aluminum and copper-clad aluminum grounding conductors are generally not permitted where in direct contact with masonry or earth, or where subject to corrosive conditions. Terminations outdoors have a minimum height requirement above earth. This effectively rules aluminum out for most electrode connections.

Electrode spacing

Where rods are used and a single rod does not meet the resistance requirement, a second is required, and rods in a group must be separated by at least 6 feet. Driving two rods 3 feet apart because that is where the conduit came out is a citation.

The electrode system, briefly

All electrodes present at a building must be bonded together into a single grounding electrode system. That includes:

  • A metal underground water pipe in direct contact with earth for the required length
  • The metal frame of the building where it qualifies
  • A concrete-encased electrode, where present in the foundation
  • A ground ring, where installed
  • Rod, pipe and plate electrodes

You do not get to pick your favorite. If a qualifying electrode exists at the building, it goes in the system. A metal water pipe electrode additionally requires a supplemental electrode.

Concrete-encased electrode timing. If the footing is being poured, that is your one chance. Coordinate with the concrete contractor before the pour and stub the conductor out where you can reach it later. Retrofitting one is not practical, and the fallback is usually rods.

Quick check before you close the panel

  • GEC sized from the service conductors, then capped by electrode type where applicable.
  • EGC sized from the overcurrent device, and increased if the phase conductors were upsized.
  • No splices in the GEC except by permitted means.
  • Ferrous raceway around the GEC bonded at both ends.
  • All present electrodes bonded into one system.
  • Main bonding jumper installed at the service, and only at the service.
  • Downstream panels have grounds and neutrals separated.

That last one and the main bonding jumper are the two that turn up most often on the common violations list, and both belong on your rough-in walkthrough.

GROUNDING SPECS, OFFLINE

GEC and EGC tables in the app, no signal required. Free tier.

// Free Download

GET THE FIELD PACK

Two printables: the 22-point rough-in checklist, and branded panel schedules in 24, 30 and 42 circuit that print at 4 by 5 inches and slide straight into a panel sleeve. Enter your email and the downloads open right away.

Your address comes straight to Jason. No list rental, no spam, unsubscribe any time.

Frequently asked questions

What is the difference between a GEC and an EGC?
The grounding electrode conductor connects the system to the earth electrode and is sized from the service entrance conductors using Table 250.66. The equipment grounding conductor runs with the circuit conductors to provide a fault return path and is sized from the overcurrent device using Table 250.122. They do different jobs and are almost never the same size.
Why is my GEC capped at 6 AWG for a ground rod?
Because the code caps the required GEC size for specific electrode types regardless of what the table would otherwise require. A connection to a rod, pipe or plate electrode is not required to be larger than 6 AWG copper. Concrete-encased and ground ring electrodes have their own caps.
Can the GEC be aluminum?
Yes, with restrictions on where it may be installed. Aluminum and copper-clad aluminum grounding conductors are generally not permitted in direct contact with masonry or earth, or in corrosive conditions, and there is a minimum height requirement above earth for terminations outdoors.
Does the GEC have to be continuous?
It has to be installed without splice or joint except by specific permitted means, such as irreversible compression connectors listed for the purpose or exothermic welding. Busbars and certain bolted connections are also permitted.

Keep reading

Calculators

Wire Size Chart: Conductor Ampacity Under NEC 310.16

Read it →
Field Tips

The 10 Most Common Electrical Code Violations

Read it →
Field Tips

Rough-In Inspection Checklist: 22 Things to Check Before You Call

Read it →
Calculators

Transformer Sizing: kVA, Primary and Secondary Current

Read it →
// DisclaimerThe National Electrical Code® (NEC®) and NFPA 70® are registered trademarks and copyrighted publications of the National Fire Protection Association (NFPA). This article is an independent educational resource and is not affiliated with, endorsed by, or sponsored by the NFPA. All code references in this article are paraphrased for educational purposes only and do not reproduce the official text of any NEC edition. This content is not a substitute for the official NFPA 70 publication. Electricians, contractors, and students are encouraged to purchase the official National Electrical Code from the NFPA at nfpa.org for complete and authoritative code text. Always verify requirements with the code edition adopted by your jurisdiction and your Authority Having Jurisdiction (AHJ).